Question: To account for uncertainties associated with activity implementation, the reserve analysis method is widely used. In reserve analysis a percentage of an estimated activity duration
To account for uncertainties associated with activity implementation, the reserve analysis method is widely used. In reserve analysis a percentage of an estimated activity duration is added as an activity buffer to account for uncertainties. An activity initially has an estimated duration of 10 days, you have decided to apply a buffer of 20%, what is the new estimated duration for this activity?