To answer this question you will need to use the standard normal table presented below ... A project's critical path has an expected duration of 60 days with a standard deviation of 6 days. If we wanted to promise a completion time that we'd be 90.32% sure we could live up to, what should that promised completion time be? (Round to 2 decimal places)