Question: To be clear, for activity 8 the predecessors are 4, 5, and 6. Both activities 1 and 2 can be started at the same time

To be clear, for activity 8 the predecessors are 4, 5, and

To be clear, for activity 8 the predecessors are 4, 5, and 6. Both activities 1 and 2 can be started at the same time as they have no predecessor.

Thank you!

Current Attempt in Progress Use the project activities that follow to determine the following: (a) Construct a Gantt chart; indicate the project completion time and slack for each activity. (Do not leave any answer field blank. Enter 0 for values.) Project completion time weeks Activity Slack (weeks) 1 2 3 4 5 6 7 8 9 eTextbook and Media Attempts: 0 of 3 used Using multiple attempts will impact your score. 25% score reduction after attempt 1 (b) The parts of this question must be completed in order. This part will be available when you complete the part above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!