Question: To define a work breakdown structure is essentially to break down a project into smaller subprojects such that the sum of the smaller subprojects defines
To define a work breakdown structure is essentially to break down a project into smaller subprojects such that the sum of the smaller subprojects defines the larger project. This process may also be referred to as subdividing or decomposition. We continue this subdividing process until we feel comfortable that we have defined work packages that are both ______ and _______.
A. manageable; simple
B. measurable; complex
C. manageable; measurable
D. simple; complex
Step by Step Solution
3.40 Rating (156 Votes )
There are 3 Steps involved in it
The detailed answer for the above question is provided below The correct answer is C manageable and ... View full answer