Question: To develop the close coordination needed for just - in - time ( JIT ) inventory control systems, manufacturers tend to rely on one supplier.
To develop the close coordination needed for justintime JIT inventory control systems, manufacturers tend to rely on one supplier. Which of the following is the criterion based on which the supplier is selected?
Group of answer choices
the size of the operation
the ability to be flexible
product quality
lowest itembyitem cost
lowest overall cost
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock