Question: To find the capacity for a process with multiple flow units, demand rates, and different paths through the process flow diagram, we need to find
To find the capacity for a process with multiple flow units, demand rates, and different paths through the process flow diagram, we need to find the bottleneck which is:
Multiple Choice
-
The resource with a utilization of 100%
-
The resource with the largest total demand rate
-
The resource with the highest implied utilization
-
The resource with the lowest capacity