To the teas surprise, the tasks on the critical path are taking less time than scheduled. It
Fantastic news! We've Found the answer you've been seeking!
Question:
- To the tea’s surprise, the tasks on the critical path are taking less time than scheduled. It now appears that the project completion will occur much earlier than the expected completion date.
- What is the impact on the schedule?