Question: Together with your team, you applied three - point estimation on a critical path which consists of three activities. The duration uncertainties ( standard deviation

Together with your team, you applied three-point estimation on a critical path which consists of three activities. The duration uncertainties (standard deviation) for the three tasks are calculated and are: 8,6, and 4. Applying the PERT formula for paths, what is the duration uncertainty of the entire path? 1 point 4.2410.7718 It is not possible to answer from the information given