Question: Tom considers himself a conservative project manager, so he never accepts deadlines that provide a safety margin below 85%. The project management software used by

Tom considers himself a conservative project manager, so he never accepts deadlines that provide a safety margin below 85%. The project management software used by my company estimates that a new project has an average duration of 40 weeks and a standard deviation of 2.5 weeks. Given Tom's assumption, what would the most appropriate duration for the project be?