Tom Heaton is a project manager with a project management company in Sudbury. The company has landed a major project. The activities that must be performed for the project, their immediate predecessors and estimated activity times (in weeks) are shown in the table below.
| Activity | Precedent | Duration (weeks) |
| A | -- | 2 |
| B | A | 6 |
| C | A | 3 |
| D | B | 4 |
| E | C, D | 5 |
| F | D | 4 |
| G | F | 3 |
| H | E, G | 2 |
- Clearly show the values for the ES, EF, LS, LF and Slack Time for All activities.
- Determine which path is the critical path? and, how long?