Question: Tom Heaton is a project manager with a project management company in Sudbury. The company has landed a major project. The activities that must be

Tom Heaton is a project manager with a project management company in Sudbury. The company has landed a major project. The activities that must be performed for the project, their immediate predecessors and estimated activity times (in weeks) are shown in the table below.

Activity

Precedent

Duration (weeks)

A

--

2

B

A

6

C

A

3

D

B

4

E

C, D

5

F

D

4

G

F

3

H

E, G

2

  1. Clearly show the values for the ES, EF, LS, LF and Slack Time for All activities.
  2. Determine which path is the critical path? and, how long?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!