Question: Tom is managing a software development project in a large IT firm. According to the project essential requirements, he has written an email to one
Tom is managing a software development project in a large IT firm. According to the project essential requirements, he has written an email to one of the functional managers and requested a number of staff to be assigned to his project on a permanent basis for a week period. The functional manager has rejected Tom's request. What should Tom do in this situation
Record this as a risk in the risk register a Change the sequence of activities so that he can cope with the b resource limitations
Raise the issue to higher level managers who can decide on project c priorities
Negotiate with the functional manager d