Question: Tomasini Corporation has provided the following data from its activity-based costing accounting system: Supervisory wages $ 660,000 Factory supplies $ 280,000 Distribution of Resource Consumption

Tomasini Corporation has provided the following data from its activity-based costing accounting system:

Supervisory wages $ 660,000
Factory supplies $ 280,000

Distribution of Resource Consumption across Activity Cost Pools:

Activity Cost Pools Batch Processing Unit Processing Other Total
Supervisory wages 20% 70% 10% 100%
Factory supplies 45% 35% 20% 100%

The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs that are not assigned to products.

How much supervisory wages and factory supplies cost would be assigned to the Batch Processing activity cost pool?

Multiple Choice

  • $305,500

  • $258,000

  • $470,000

  • $940,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!