Question: Tommy is a project manager in a software project. He wants to assess high - level risks. What should he do ? Group of answer

Tommy is a project manager in a software project. He wants to assess high-level risks. What should he do?
Group of answer choices
Develop contingency plans and fallback plans in case the original plan proves wrong.
Develop the project charter and a risk management plan to start identifying risks based on those and other documents
Do nothing.
Discuss the risks documented in your Risk register with the project key stakeholders.