Question: Top - down estimates ( You may select more than one answer. Single cllck the box with the qu for a correct answer and double

Top-down estimates (You may select more than one answer. Single cllck the box with the qu for a correct answer and double cllck the box with the question mark to empty the box for question mark wIII be automatically graded as incorrect.)
are used in the project conceptual phase
depend on surrogate measures such as weight or square feet or ratios
do not consider individual activity issues and problems
are good for rough estimates
can help select and prioritize projects
are made by people familiar with the task
help to gain buy-in on the validity of the estimate
improve the accuracy of the estimate
? should be preferred if estimating cost is reasonable
 Top-down estimates (You may select more than one answer. Single cllck

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!