Question: Topic 1 : In the following process, customer orders arrive at a rate of 5 units per hour. Machine 1 Machine 2 Machine 3 Machine

Topic 1:
In the following process, customer orders arrive at a rate of 5 units
per hour.
Machine 1
Machine 2
Machine 3
Machine 4
5 units/hour
What is the utilization of the process?
3 units/hour
4 units/hour
6 units/hour
100%
60%
80%
120%