Question: Topic 2 Assignment Saved Help Save & Exit Submit Check my work 2 The following activities are part of a project to be scheduled using


Topic 2 Assignment Saved Help Save & Exit Submit Check my work 2 The following activities are part of a project to be scheduled using CPM: IMMEDIATE TIME ACTIVITY PREDECESSOR (WEEKS) 2 points A B Skipped C D MOWODDI V W A N VWO eBook B, D Hint E , F Print References b. What is the critical path? O A-C-D-E-G O A-B-E-G O A-C-D-F-G Mc Graw HillTopic 2 Assignment Saved Help Save & Exit Submit Check my work 2 MULL O A-C-D-F-G 2 points c. How many weeks will it take to complete the project? Skipped Number of weeks eBook Hint Print References d. How much slack does activity B have? Slack of activity B weeks Mc Graw Hill