Question: Topic a: EVM Cost and Schedule Variances and Performance Indices Suppose Jon has a project consisting of three activities. Midway through the project, he collects

Topic a: EVM Cost and Schedule Variances and Performance Indices

Suppose Jon has a project consisting of three activities. Midway through the project, he collects the following information:

Activity

PV

EV

AC

1

30

40

35

2

20

15

15

3

10

10

15

-What are the project-level Schedule Variance (SV) and Cost Variance (CV)?

- What are the project-level Schedule Performance Index (SPI) and Cost Performance Index (CPI)?

- Under what conditions would a positive variance and a performance index less than 1.0 co-occur?

Topic b: Corrective Action

Describe any performance "thresholds" an organization uses to signal when corrective action is required to get a project back on track.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!