topic is project management
topic is project management
topic is project management
\begin{tabular}{|c|c|c|c|c|c|} \hline Task & Predecessor & Normal time (days) & Normal cost (\$) & Crash time (days) & Crash cost (\$) \\ \hline A & & 6 & 300 & 6 & \\ \hline B & A & 8 & 400 & 6 & 600 \\ \hline C & A & 6 & 500 & 4 & 620 \\ \hline D & B, C & 8 & 400 & 6 & 480 \\ \hline E & C & 4 & 500 & 4 & \\ \hline F & B & 6 & 400 & 2 & 520 \\ \hline G & F & 4 & 500 & 2 & 540 \\ \hline H & D, E & 8 & 600 & 4 & 840 \\ \hline I & G, H & 4 & 400 & 2 & 800 \\ \hline \end{tabular} 4. Crash the project to its minimum duration (the fastest it can be completed) a. For the following paths indicate to what duration can each be crashed, and if they need to be fully crashed: - Path A to G - Path A to H b. Total duration of the project crashed to its minimum. c. Total cost to crash the project to its minimum duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!