Question: Topic: Line Balancing Solve the following problem; show your solution (15 points) Problem 1. (5 points) A local manufacturing firm's assembly line has 18 tasks

Topic: Line Balancing Solve the following problem; show your solution (15 points) Problem 1. (5 points) A local manufacturing firm's assembly line has 18 tasks which need to be balanced. The longest task is 2.5 minutes, and the total time for all tasks is 18 minutes. The line will operate for 400 minutes per day. What range of output is theoretically possible for the line? Problem 2 (10 points) Given: Available Processing time =8 hours / day; Daily demand =50 chairs a. Draw the precedence diagram b. What is the cycle time c. What is theoretical number of workstations d. What is the total idle time e. What is the efficiency? Balance delay