Question: Topic: PERT chart The activities shown below have been identified for the making of a new album of a popular J- Pop Group, called Kukuro.

Topic: PERT chart
The activities shown below have been identified for the making of a new album of a popular J- Pop Group, called Kukuro. Activity completion times and their precedence relationship have also been provided. Table 1. Activity information of the making of Kukuro's album. Activity Time (Weeks) Immediate Predecessor(s) A 10 B 8 9 A 7 A 6 B uwu UI 12 B 5 D, E 4 D, E I 8 ) 7 K 5 GI L 7 F, H a) Draw the network diagram. b) Calculate slack for each activity. c) Determine the critical path and the project duration. (12 marks) (8 marks) (4 marks)Step by Step Solution