Question: Total = 6 points, part a = 3 points; parts b = 2 points and part c 1 point. Consider the following project. Use activity
Total points, part a points; parts b points and part c point.
Consider the following project. Use activity times as the most likely time for determining the critical path. Use the optimistic and pessimistic times together with activity times to determine expected completion time limits
a Draw PERT Chart with earliest and latest start and finish timesactivity Fill in the slack time in the table for each activity. Show the slack time for each path for all paths and show Critical Path CPM and CPM time.
b What is the expected time for and percent Confidence Interval CI for the project?
c Show the ID ID ID ID ID ID ID ID ID Confidence Interval for the project use section page for parts for only one percentage corresponding to your ID not all percentages.
tableID Preceeding,Start,End,Activity,Stafi,Optimistic,PessimisticActivityActivity,Node,Node,Time,Required,Time,TimeASBSCSDA B BEBFEEnd,GC EEnd,HDEnd,
Notes:
This problem contains two Dummy activities.
You can use Microsoft Project software for solution to this problem, but please show dummy activities in your solution.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock