Question: Total Marks = 3 0 Marks , Duration = 1 hour 1 5 minutes ( 6 : 3 0 P M t o 7 :

Total Marks =30 Marks , Duration =1 hour 15 minutes (6:30PMto7:45PMon March 10,2024)
Q1. The statements below may be true or false. If the statement is TRUE, mention the underlined word(s). If the statement is FALSE, mention the corrected word(s) against the underlined word(s). The correction should be done in such a way that the entire sentence becomes TRUE. For answers, use the table format given at the end of all statements.
You are NOT allowed to change/replace the non-underlined part of the sentence. DO NOT write TRUE or FAI SE as answers.
a) Make-to-order (MTO) processes are mostly Pull system based, while Make-to-stock (MTS) processes are mostly Push [B] system based.
b) In relation to the product-process matrix, Modular design is generally associated with and Delayed product differentiation is generally associated with Continuous flow B.
c) Refurbishing A is associated with the use of good quality material and Recycling B is associated with use of good quality parts of a product in another product.
d) In the context of capacity, an increase in unplanned downtime decreases Utilization only A, whereas an increase in planned downtime decreases both Utilization and Efficiency [B].
e) FSN inventory classification method suggests discounts for fast A moving items and sales even at loss for slow [B] moving items.
f) As per Bathtub curve analysis, both A infant mortality and random failure phases B are considered for the warranty period.
g) The Shortest Processing Time (SPT) rule minimizes both machine Makespan [A] and Total waiting [B] time.
h) As per Juran, a worker will be responsible for producing defective items if all the following are applicable: the worker designs A SOP, the worker receives feedback in real-time, and management has control B over the working environment.
i) Indications of problem in the control charts include randomness in data and sudden increase in precision [B].
Write your answers after creating EXACTLY the same table format given below. If any space on the table prepared by you remains empty, it will be considered the answer is not known. Even if the underlined word in the question is correct, you need to write it in the table. Each sentence carries 2 Marks.
 Total Marks =30 Marks , Duration =1 hour 15 minutes (6:30PMto7:45PMon

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!