Question: Toyota is analyzing its performance using a flexible budget. The following data is available: Cost Category Budgeted Cost ($) Actual Cost ($) Direct Materials $700,000

Toyota is analyzing its performance using a flexible budget. The following data is available:

Cost Category

Budgeted Cost ($)

Actual Cost ($)

Direct Materials

$700,000

$690,000

Direct Labor

$480,000

$490,000

Variable Overhead

$350,000

$340,000

Fixed Overhead

$600,000

$620,000

Calculate the flexible budget variance for each cost category.