Toyota is analyzing its performance using a flexible budget. The following data is available:
Cost Category | Budgeted Cost ($) | Actual Cost ($) |
Direct Materials | $700,000 | $690,000 |
Direct Labor | $480,000 | $490,000 |
Variable Overhead | $350,000 | $340,000 |
Fixed Overhead | $600,000 | $620,000 |
Calculate the flexible budget variance for each cost category.