Question: Tracking work by time period allows the project manager to perform a more detailed level of tracking; It is best to use time phased tracking
Tracking work by time period allows the project manager to perform a more detailed level of tracking; It is best to use time phased tracking except in which of the following circumstances? Question 22 options: When there is insufficient time and money to perform detailed tracking. When you are tracking progress on near critical tasks. There are high risk tasks involved. Tasks in which key stakeholders have a high interest level