a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time
Fantastic news! We've Found the answer you've been seeking!
Question:
- a) Draw a precedence diagram of this operation.
- b) Given the demand, what is the cycle time for this operation?
- c) What is the theoretical minimum number of workstations?
d) Assign tasks to workstations.
e) How much total idle time is present each cycle?
f) What is the efficiency of the assembly line with five stations? With six stations?rn