Question: A large central heating system repair company has been monitoring the number of call-outs where an engineer has been unable to resolve a problem, leading


A large central heating system repair company has been monitoring the number of call-outs where an engineer has been unable to resolve a problem, leading to the need for a second visit. The company prides itself on the quality of service it provides and would like to restrict the number of unresolved call-outs to 10 per day. What is the upper action line (i.e. upper control limit) for a suitable control chart for this case? Provide your answer to the nearest two decimal places