Question: A project manager is using the payback method to make the final decision on which project to undertake. The company has a 20% required rate
A project manager is using the payback method to make the final decision on which project to undertake. The company has a 20% required rate of return and expects a 3% rate of inflation for the following five years. What is the discount factor for Year 3? O 0.66 0.81 O 0.44 0.54