Question: Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow -100 40 50 60 N/A -73 30 30 30 A B Discount Rate 0.12 0.12 30 The profitability index for project B is closest to: O A. 0.25 O B. 37.23 O C. 24.82 OD. 0.15