Question: Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty variable utilities costs per machine hour. Round

 Given the following cost and activity observations for Bounty Company's utilities,

use the high-low method to calculate Bounty variable utilities costs per machine

Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty variable utilities costs per machine hour. Round your answer to the nearest cent. Cost Machine Hours March $3.100 15.000 April 2,700 10,000 May 2.900 12.000 June 3.600 18.000 O a. $0.63 O b. $0.67 O c. $0.11 O d. $10.00