Question: Match the following: 1. A specific task or sets of tasks that Activity Network Critical Path Event are required by the project, use up resources,

Match the following: 1. A specific task or sets of tasks that Activity Network Critical Path Event are required by the project, use up resources, and take time to complete. 2. The result of completing one or more activities. 3. The arrangement of activities that defines a project and the activity precedence relationships. 4. The series of connected activities. 5. If delayed, will delay the completion of the project