Question: Question 14 9.5 pts Applying the discounted payback decision rule to all projects may cause: some projects to be accepted which would otherwise be rejected

Question 14 9.5 pts Applying the discounted payback decision rule to all projects may cause: some projects to be accepted which would otherwise be rejected under the payback rule. some positive net present value projects to be rejected. projects to be incorrectly accepted due to ignoring the time value of money. the most liquid projects to be rejected in favor of the less liquid projects