Question: Question 2: Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for
Question 2: Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $2,000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. What is the optimum cost-time schedule for the project? Note: The correct normal project duration and total direct cost are provided. Show ALL of your working to get the points ( 30pts)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
