Question: The following information is given for the last month's operation: Actual run time this week Machine time available this week Actual run rate this week
The following information is given for the last month's operation: Actual run time this week Machine time available this week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 4,500 minutes 5,000 minutes 3.6 units per minute 4.0 units per minute 13,600 units 16,200 units 5.14 The overall equipment effectiveness (OEE) is closest to: Multiple Choice 068 0.53 0.60
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock