Question: True / False [ 1 point each ] _ An item after being processed by the first operator is set aside in the buffer (

True/False [1 point each]
_ An item after being processed by the first operator is set aside in the buffer (a temporary storage area) waiting for the second operator to pick up, this activity is considered a "storage".
For each activity (operation or inspection) in the operation process chart, an estimate should be made of the time it will take to complete the activity.
Design for Manufacture is also known as House of Productivity.
A routing sheet is also known as a production work order.
CAGR is an accounting term used to describe some element of the business, for example revenue, units delivered, registered users, etc.
The tolerance may be defined as +-3 to 6 of the natural production process.
_ The first step for implementing QFD is to draw a Fishbone diagram.
_ When takt time is increased workers can be assigned to attend more machines to accommodate the demand and this can only be accomplished in a U-shaped manufacturing cell.
__ In calculating the unit production time, the setup time can be ignored if the production volume is huge, for example over 100,000 units.
_ The Machine Coupling technique may be applied in the kitchen of a fast food restaurant to improve the efficiency of the kitchen.
Multiple choice [2 points each.]
q, Which of the following operations is not part of an assembly operation?
(a) retrieve components from storage (b) handle the components to orient them relative to each other (c) retrieve assembly tools and position them on components (d) mate components (e) All of them are elements of an assembly operations. q, It is known that the defective ratio of an EDM machine is 0.7%. How many units of raw materials should be fed into it if 1000 good parts need to be produced?
(a)1005(b)1006(c)1007(d)1008(e)1009
q, Where is "the interrelationships" located in a House of Quality?
(a) roof (b) front (c) second floor (d) back (e) basement
q, Takt time is
(a) the cycle time of the bottleneck station (b) the available work time per day (c) the time needed to produce the product batch to meet the customer demand (d) the shortest station time (e) the time needed to product one unit of product to meet the customer demand
Which of the following may not be changed in a cellular manufacturing system to adjust for demand changes?
(a) number of worker (b) number of machine (c) machine output rate (d) machine cycle time (e) takt time
 True/False [1 point each] _ An item after being processed by

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!