Question: TRUE or FALSE: PERT and CPM techniques work by determining the critical path for the completion of a series of interrelated activities. If any of
TRUE or FALSE:
PERT and CPM techniques work by determining the "critical path" for the completion of a series of interrelated activities. If any of the activities along the critical path is delayed, the entire project is delayed.