Question: True or False? Under nationally published General Conditions, the Contractor is solely responsible for the means, techniques, and sequences of construction. Group of answer choices

True or False? Under nationally published General Conditions, the Contractor is solely responsible for the means, techniques, and sequences of construction. Group of answer choices True False