Question: Try to develop a new heuristic methodology to solve the flow shop problem. Explain the idea of your methodology. Determine the steps of your methodology.

Try to develop a new heuristic methodology to solve the flow shop problem. Explain the idea of your methodology. Determine the steps of your methodology. Solve the problem with your proposed methodology and find the best sequence and Cmax. Solve the problem by using Branch& Bound algorithm and CDS algorithm. Compare the results with your proposed methodology and calculate the effectiveness of your proposed methodology.
END3760 Scheduling Project There is a 5 jobs 3 machines flow shop problem. M1 J1 J2 J3 27 12 11 8 14 M2 10 9 10 13 12 8 10 8 12 9 J4 J5 Try to develop a new heuristic methodology to solve the flow shop problem. Explain the idea of your methodology. Determine the steps of your methodologyStep by Step Solution