Question: Try valuing a project with the following estimates for year 2: Taxable Income (EBIT) 50 Tax Rate 35% Allocated R&D costs* 10 Depreciation 10 Year
Try valuing a project with the following estimates for year 2:
Taxable Income (EBIT) 50
Tax Rate 35%
Allocated R\&D costs* 10
Depreciation 10
Year 1 Net Working Capital 20
Year 2 Net Working Capital 15
*Reflects costs that have already been incurred, assigned to year 2 of the project.
What is the total Free Cash Flow in year 2?