Question: Turn the following SOP into a Process Map: Extra point for swim-lane Distribution Management 1: Receive production order from manufacturing facility 2: Manufacturing facility loads
Turn the following SOP into a Process Map: Extra point for swim-lane
Distribution Management
1: Receive production order from manufacturing facility
2: Manufacturing facility loads product on trailer
3: Manufacturing facility ships order to distribution centre
4: Order received at distribution centre
5: Product unloaded
6: Product placed in waiting trailers
7: Add shipping manifest to trailers
8: When customer trailer full ship to customer
9: Communicate shipping order to customer
10: Order received by customer
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts