Question: Turner Inc. began work on a $7,000,000 contract in 2012 to construct an office building. During 2012, Turner Inc., incurred costs of $1,700,000, billed its
Turner Inc. began work on a $7,000,000 contract in 2012 to construct an office building. During 2012, Turner Inc., incurred costs of $1,700,000, billed its customers for $1,200,000, and collected $960,000. At Dec. 31,2012, the estimated future costs to complete the project total $3,300,000. Prepare Turners's 2012 journal entries using the percentage of completion method.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts