Question: TUTORIAL 7 - IFS 2 3 3 ( 2 0 2 4 ) Tutorial Homework Additional Information The project starts with three activities - A

TUTORIAL 7- IFS233(2024)
Tutorial Homework
Additional Information
The project starts with three activities-A, C, and
D-which can be done concurrently.
When A is finished, B can start
When B is finished, E can start
When C is finished, F can start
When both B and D are finished, G can start
When E is finished, H can start
When F is finished, I can start
When both E and G are finished, J can start
When both F and H are finished, K can start
When I is finished, L can start
When J,K and L are finished, M can start
The project is complete when M is finished
Questions
Organize the information above in an activity precedence table.
Draw an Activity-On-Arrow (AOA) network diagram representing information shown on
the activity precedence table.
Show all different paths and their durations.
Identify the project's critical path and its length?
(Assume all durations are in days)
Remember to complete and submit your tutorial to your tutor
TUTORIAL 7 - IFS 2 3 3 ( 2 0 2 4 ) Tutorial

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!