Question: Two activities for a project and their optimistic completion times (a), most likely completion times (m), and pessimistic completion times (b) are given in days

Two activities for a project and their optimistic
Two activities for a project and their optimistic completion times (a), most likely completion times (m), and pessimistic completion times (b) are given in days in the below table Activity A B Time (days) a m b 4 7 12 10 11 15 Calculate the expected activity time and standard deviation for each activity in days using PERT: (round your responses to two decimal places) Activity Expected Activity Standard Time Deviation A B