Question: Two alternatives, code-named X and Y, are under consideration at Brahler Corporation. Costs associated with the alternatives are listed below. Materials costs Processing costs Equipment

 Two alternatives, code-named X and Y, are under consideration at Brahler

Two alternatives, code-named X and Y, are under consideration at Brahler Corporation. Costs associated with the alternatives are listed below. Materials costs Processing costs Equipment rental Occupancy costs Alternative x $ 39,000 $ 44,000 $ 10,000 $ 15,000 Alternative Y $ 39,000 $ 58,000 $ 10,000 $ 29,000 What is the differential cost of Alternative Y over Alternative X, including all of the relevant costs? $108,000 $122,000 $28,000 $136,000