Question: Two bids are submitted for a project. Contractor A ' s total was $ 2 5 0 , 0 0 0 and Contractor B '
Two bids are submitted for a project. Contractor As total was $ and Contractor Bs total was $ Contractor A was selected for the project and began work. However, after the work began, Contractor A needed to revise his bid to $ due to a material price error. Since this revision will take place after the work has begun, he cannot revise his contract.
True
False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
