Question: Two bids are submitted for a project. Contractor A ' s total was $ 2 5 0 , 0 0 0 and Contractor B '

Two bids are submitted for a project. Contractor A's total was $250,000 and Contractor B's total was $260,000. Contractor A was selected for the project and began work. However, after the work began, Contractor A needed to revise his bid to $255,000 due to a material price error. Since this revision will take place after the work has begun, he cannot revise his contract.
True
False