Question: Two projects are given with a required return of 12%. NOTE: See below, do NOT calculate, interpet! Year Project A Project B 0 $ (20,000)
Two projects are given with a required return of 12%. NOTE: See below, do NOT calculate, interpet!
| Year | Project A | Project B |
| 0 | $ (20,000) | $ (20,000) |
| 1 | $ 12,000 | $ 7,000 |
| 2 | $ 10,000 | $ 9,000 |
| 3 | $ 5,000 | $ 13,000 |
| NPV | $ 2,245 | $ 2,678 |
| IRR | 19.4% | 18.9% |
Group of answer choices
choose Project B, IRR is not reliable due to timing of CFs
choose Project B, IRR is not reliable due to project scale
choose Project A, IRR is greater