Question: Two projects have the following projected cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$105,000 -$150,000 1 $30,000 $30,000 2
Two projects have the following projected cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$105,000 -$150,000 1 $30,000 $30,000 2 $45,000 $30,000 3 $30,000 $40,000 4 $15,000 $50,000 5 $44,500 $87,000 Both projects have a salvage value at the end of year 5 of $20,000 Calculate the NPVs and IRRS of each project, if the WACC is 6% and if it is 11%. Then answer the questions that follow. You may find it useful to enter your answers in the following table: Project B Project A Project B Project A @6% WACC @ 6% WACC @11% WACC @11% WACC NPV IRR Screenshot 2024-04-... NPV & IRR Q Refer to the NPV & IRR Scenario above. What is the Future Value of Project A if the WACC is 11%? 48,267 $64,349 $103,818 $71,701 $97,323