Question: Two specific methods used to plan out and then measure progress in the control of a manufacturing process are called Gantt and PERT charts. ERP

Two specific methods used to plan out and then measure progress in the control of a manufacturing process are called
Gantt and PERT charts.
ERP and MRP systems.
JIT and UPS.
Baldridge and Six Sigma systems.
ISO 9001 and ISO 14000.
 Two specific methods used to plan out and then measure progress