Question: Type or paste question here Please use given MRP planning schedule for item J to answer the following questions: Unit Cost $20 Setup cost $60
Type or paste question here
Please use given MRP planning schedule for item J to answer the following questions:
| Unit Cost | $20 |
| Setup cost | $60 |
| Inventory holding cost per week | 1.5% of unit cost |
| Beginning inventory | 60 |
| Lead time | 1 week |
| Week | 0 | 1 | 2 | 3 | 4 | 5 |
| Demand |
| 45 | 38 | 60 | 80 | 25 |
- Select adequate EOQ model to calculate the optimal order quantity___ (round up to the nearest whole number).
- Indicate the correct net requirements, planned-order receipts, and planned order releases to meet the demand in the provided table.
- Calculate the total inventory holding cost and fixed ordering cost for these 5 weeks in the provided table
|
| Week: | 0 | 1 | 2 | 3 | 4 | 5 | TC | ||
| Item: |
| Gross requirements |
|
|
|
|
|
|
| |
| OH: |
| Scheduled receipts |
|
|
|
|
|
|
| |
| LT: |
| Projected available balance |
|
|
|
|
|
|
| |
| SS: |
| Net requirements |
|
|
|
|
|
|
| |
| Q: |
| Planned order receipts |
|
|
|
|
|
|
| |
|
|
| Planned order releases |
|
|
|
|
|
|
| |
| Inventory Holding Cost |
|
|
|
|
|
|
| |||
| Fixed Ordering/Set-up Cost |
|
|
|
|
|
|
| |||
|
|
|
|
| |||||||