Question: Type your answer in the box. Activity Cost Pools and Measures Estimated Overhead Expected Activity Machine maintenance (Machine hours) $400,000 150,000 machine hours Machine setups

Type your answer in the box. Activity Cost Pools and Measures Estimated Overhead Expected Activity Machine maintenance (Machine hours) $400,000 150,000 machine hours Machine setups (Number of setups) $150,000 1,200 setups Direct labor support (Direct labor hours) $920,000 200,000 direct labor hours (Enter your answer as a Based on this information, the activity rate for Machine Setups is $ whole number.)