Question: U VUN Question 6 (13 points) A software development project that you are managing has a budget at completion of 436,000. At month seven, 67%

U VUN Question 6 (13 points) A software
U VUN Question 6 (13 points) A software development project that you are managing has a budget at completion of 436,000. At month seven, 67% of the work was planned to be completed but stands at 49%. The actual cost is 221,000. What is the project's Estimate to Complete (ETC)? (Do not write the unit in your answer) Your